How do I view and adjust the duration of the utilization summary chart for heavy equipment?

  • Updated

Roles: Administrator & Employee | Interface: Web, Mobile

The Summary chart displays utilization for a default 30-day period. Adjust the duration to view utilization over different time frames.

Instructions:

Web Platform:

  • Go to the "Asset" and search for the required heavy equipment asset.
  • Scroll down to the Asset Details section and open Utilization.
  • Open it to view utilization of the asset, including idle time, working hours, and engine off hours.
  • You can adjust the time span to 7 or 30 days, or customize it as needed. The maximum date range is 1 year from the current date.

Mobile Application:

  • Open the dashboard, click "Assets". The asset list will open. Search for and select the heavy equipment asset you need.

  • Here, you can see percentages and time periods for working hours, idle time, and engine-off time. Adjust the duration to see how these times change.

Note:

The "Idle" legend will only appear if there is idle data received. If no idle data is present, the "Idle" legend will not be shown at the bottom of the chart.

 

line 2.png

If you are interested to learn how to see utilization for heavy equipment, please check: How do I see utilization for heavy equipment?

If you are interested to learn how to view detailed utilization and adjust the duration on the chart to see different date ranges, please check: How do I view detailed utilization and adjust the duration on the chart to see different date ranges?

Related to

Was this article helpful?

0 out of 0 found this helpful